Benitez Company currently outsources a relay switch that is a component in one of its products. The switches cost $35 each. The company is considering making the switches internally at the following projected annual production costs: Unit-level material cost $ 7 Unit-level labor cost $ 6 Unit-level overhead $ 5 Batch-level set-up cost (8,000 units per batch) $ 50,000 Product-level supervisory salaries $ 50,000 Allocated facility-level costs $ 45,000 The company expects an annual need for 8,000 switches. If the company makes the product, it will have to utilize factory space currently being leased to another company for $4,000 a month. If the company decides to make the parts, total costs will be?

+2
Answers (1)
  1. 28 February, 12:13
    0
    Total costs will be $12,000 more than if the switches are purchased.

    Explanation:

    Total incremental cost:

    = Unit cost + Batch level set up cost + Product level supervisory salaries + Rental income

    = (material cost + labor cost + overhead) * Annual need for switches + $50,000 + $50,000 + ($4,000 * 12 months)

    = (7 + 6 + 5) * 8,000 + $50,000 + $50,000 + ($4,000 * 12 months)

    = $144,000 + $50,000 + $50,000 + $48,000

    = $292,000

    Present cost = Annual need for switches * cost of each switch

    = 8,000 * $35

    = $280,000

    Net increase in costs will be:

    = Total incremental cost - Present cost

    = $292,000 - $280,000

    = $12,000

    Therefore, the total costs will be $12,000 more than if the switches are purchased.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Benitez Company currently outsources a relay switch that is a component in one of its products. The switches cost $35 each. The company is ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.