Ask Question
7 February, 05:42

Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: HoursWait time 20.6Process time 1.9Inspection time 0.1Move time 2.7Queue time 4.8The manufacturing cycle efficiency (MCE) was closest to:A) 0.46B) 0.06C) 0.20D) 0.19

+3
Answers (1)
  1. 7 February, 08:23
    0
    C) 0.20

    Explanation:

    We know that,

    Process time = Manufacturing cycle efficiency (MCE) * average throughput time

    where,

    Average throughput time = Process time + Inspection time + Move time + Queue time

    = 1.9 + 0.1 + 2.7 + 4.8

    = 9.5

    And, the process time would be 1.9

    Now put these values to the above formula

    So, the efficiency would equal to

    1.9 = Manufacturing cycle efficiency (MCE) * 9.5

    So, Manufacturing cycle efficiency (MCE) would be 0.20
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: HoursWait time ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers