PERT and CPM

a. have been combined to develop a procedure that uses the best of each.

b. have different features and are not applied to the same situation.

c. do not require a chronological relationship among activities.

d. are most valuable when a small number of activities must be scheduled.

+2
Answers (1)
  1. 6 August, 00:23
    0
    Answer is option a, i. e. have been combined to develop a procedure that uses the best of each.

    Explanation:

    In project management, PERT i. e. project evaluation and review technique is used as a statistical tool that is used to assess the overall work that is done to complete a certain project. In order to complete a particular task, there can be 'n' number of paths or ways. The best decision of selecting a pathway that is time-saving as well as cost-saving is to be found out. This chosen path is then referred to as 'Critical path.' Hence, PERT and CPM can be understood as two faces of a single coin, and have been combined to develop a procedure that uses the best of each.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “PERT and CPM a. have been combined to develop a procedure that uses the best of each. b. have different features and are not applied to the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers