The Thomlin Company forecasts that total overhead for the current year will be $15,500,000 with 250,000 total machine hours. Year to date, the actual overhead is $16,000,000 and the actual machine hours are 330,000 hours. The predetermined overhead rate based on machine hours is. a. a. $48 per machine hour. b. $62 per machine hour. c. $45 per machine hour. d. $50 per machine hour.

+2
Answers (1)
  1. 2 September, 21:34
    0
    B) $62 per machine hour

    Explanation:

    To calculate the overhead rate per hour we solve the following equation:

    overhead rate per hour = $15,500,000 / 250,000 machine hours = $62 per machine hour

    if we compare this current rate per machine hour to last year's rate per machine = $16,000,000 / 300,000 machine hours = $53.33, we can determine that Thomlin is overapplying overhead expenses ($62 > $53.33).
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The Thomlin Company forecasts that total overhead for the current year will be $15,500,000 with 250,000 total machine hours. Year to date, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers