Using the Time-Cost CPM model, the crash time is the shortest possible time allowed for each activity in the project. Group of answer choices True False

+4
Answers (1)
  1. 28 June, 21:46
    0
    The answer is true

    Explanation:

    The Critical Path Method (CPM) is a project scheduling technique to analyze and represent the tasks involved in completing a given project. The critical path method assumes that the duration of an activity depends on the amount of resources assigned to it. Crash duration in CPM is the minimum duration of the activity.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Using the Time-Cost CPM model, the crash time is the shortest possible time allowed for each activity in the project. Group of answer ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.