Reyes Corporation applies overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead was $284,590, budgeted machine-hours were 19,100. Actual factory overhead was $243,830, actual machine-hours were 17,750. How much overhead would be applied to production?

+5
Answers (1)
  1. 11 September, 16:28
    0
    Amount of overheads to be applied to production = $264,475

    Explanation:

    Absorption costing

    Absorption costing is method of costing where overheads are charged to units produced using volume-based bases. e. g mahine hours, labour hours e. t. c.

    Under this costings system, inventory and completed units are valued using full cost.

    Full cost = D. Mat. + D. Lab. + Variable Prod. OH + Fixed Prod. Oh

    Step 1: Calculate the overheard absorption rate (OAR) /

    Fixed Prod OH (FPOH)

    = Budgeted overheads for the period / Budgeted machine hours

    = $284,590 / 19,100 hours

    =$ 14.9 per machine hour

    Step 2: Calculate the absorbed overheads

    Absorbed overheads = OAR * Actual machine hours

    = $264,475

    Amount of overheads to be applied to production = $264,475
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Reyes Corporation applies overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead was $284,590, ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.