Lezo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on 40,000 machine-hours, total fixed manufacturing overhead cost of $136,000, and a variable manufacturing overhead rate of $2.90 per machine-hour. Job A290, which was for 60 units of a custom product, was recently completed. The job cost sheet for the job contained the following dа ta:
Total machine-hours 300
Direct materials $585
Direct labor cost $7,200
Required:
A) Calculate the estimated total manufacturing overhead for the year.
B) Calculate the predetermined overhead rate for the year.
C) Calculate the amount of overhead applied to Job A290.
D) Calculate the total job cost for Job A290.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Lezo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.