Ask Question
13 July, 17:44

Pogmon Solutions, a computer manufacturer, is introducing a new product-a high-end gaming laptop. Its technicians take 21 hours to produce the first unit of the laptop, and the company follows a 78 percent learning curve. Given this information, the eighth unit of the laptop would approximately require?

+1
Answers (1)
  1. 13 July, 19:47
    0
    From the given question

    For production of 1 unit of Laptop technicians require 21 Hours

    Also given the learning curve is 78%

    So, to produce 8 units of laptops the time required by the technicians is

    L=0.78

    T1 = 21 hrs

    T8 = T1 (N (log L/log 2)) = 21 (8 (log 0.78/log 2))

    T8 = 21 (8 (log 0.78/log 2))
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Pogmon Solutions, a computer manufacturer, is introducing a new product-a high-end gaming laptop. Its technicians take 21 hours to produce ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers