Monica, a project manager at a software firm, learns during a status report meeting that a difference exists between the baseline scope and the actual project performance. What does Monica need to do next?

1. Propose a schedule change

2. Analyze the variance

3. Implement a scope change

4. Expand the project scope

+5
Answers (1)
  1. 22 April, 06:06
    0
    Answer: 2. Analyze the variance

    Explanation:

    As a project manager, Monica needs to first understand the differences which exists between the baseline scope and actual project performance. She needs to analyse the fact or quality of the differences and inconsistency that exists, in order to prevent potential disagreement or conflicts with the clients or company.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Monica, a project manager at a software firm, learns during a status report meeting that a difference exists between the baseline scope and ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers