Ask Question
7 February, 20:14

The processing department has monthly budgeted manufacturing overhead of $180,000 plus $3.00 per machine hour. If a flexible budget report shows $348,000 for total budgeted manufacturing overhead costs for the month, what was the actual level of activity achieved during the month?

+1
Answers (1)
  1. 7 February, 22:06
    0
    56,000 machine hours

    Explanation:

    Data provided in the question:

    Monthly budgeted manufacturing overhead = $180,000 + 3 per machine hours

    Total budgeted manufacturing overhead costs = $348,000 for the month

    Now,

    Let the actual level of activity achieved during the month be 'x'

    Therefore,

    Total budgeted manufacturing overhead costs = $180,000 + 3 (x)

    or

    $348,000 = $180,000 + $3 (x)

    or

    $3x = $348,000 - $180,000

    or

    $3x = $168,000

    or

    x = 56,000 machine hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The processing department has monthly budgeted manufacturing overhead of $180,000 plus $3.00 per machine hour. If a flexible budget report ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers