You are meeting with a customer for initial discussions about a software implementation project. At the end of the day, the customer asks you for a general estimate of the project duration. Based on your experience with three similar past projects you estimate an 8-10 month implementation time frame. What is this type of estimation technique called?

+5
Answers (1)
  1. 25 October, 00:28
    0
    The estimation technique is called comparative or analogous technique. This is because you are making project duration estimates based on previous projects

    Explanation:

    When projections for a current project is based on the outcome and results of past projects, then a comparative estimation is being done.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “You are meeting with a customer for initial discussions about a software implementation project. At the end of the day, the customer asks ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers