15 December, 15:00

The following information was collected on work Center 40: 400 hours scheduled; 30 hours lost due to absenteeism; 20 hours lost while waiting for tooling; 40 hours lost due to power failure; and 300 standard hours of production achieved. Calculate the work center utilization.

+2
Answers (1)
  1. 15 December, 18:43
    0
    75% is the work center utilization

    Explanation:

    Mathematically;

    Utilization = (Actual Output/Design capacity) * 100

    From the question;

    Actual output = 300

    Design capacity = 400

    Substituting these values in the equation, we have:

    = (300/400) * 100

    = 0.75*100

    = 75%
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The following information was collected on work Center 40: 400 hours scheduled; 30 hours lost due to absenteeism; 20 hours lost while ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.