Ask Question
17 August, 19:11

Craydye makes all sorts of moldings. Its standard quantity of material allowed is 1 foot of wood per 1 foot of molding at a standard price of $3.00 per foot. During August, it purchased 200,000 feet of wood at a cost of $2.00 per foot, which produced only 199,000 feet of molding. Calculate the materials price variance and the materials usage variance. a.$600,900 U and $2,500 F b.$200,000 F and $3,000 U c.$400,000 F and $1,000 U d.$700,000 U and $4,000 F

+5
Answers (1)
  1. 17 August, 23:11
    0
    We choose b.$200,000 F and $3,000 U

    Explanation:

    Given that:

    standard price of $3.00 per foot purchased 200,000 cost of $2.00 per foot produced only 199,000 feet of molding

    Material Price Variance

    = (Standard Price X Actual Quantity) - (Actual Price X Actual Quantity)

    = ($ 3*200000) - ($ 2*200000)

    = $ 600000 - $ 400000

    = $ 200000 F

    Material Usage variance

    = (Standard Price X Standard Quantity) - (Standard Price X Actual Quantity)

    = ($3 * 199000) - ($3*200000)

    = $ 597000 - $ 600000

    = $ 3000 U

    We choose b.$200,000 F and $3,000 U

    Hope it will find you well
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Craydye makes all sorts of moldings. Its standard quantity of material allowed is 1 foot of wood per 1 foot of molding at a standard price ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers