Ask Question
24 November, 05:24

The company allocates manufacturing overhead using a single plantwide rate with machine hours as the allocation base. Estimated overhead costs for the year are $108,000. Additional estimated information is given below.

Normal Premium

Machine hours (MHr) 29,000 48,000

Direct materials $58,000 $440,000

Calculate the predetermined overhead allocation rate. (Round your answer to the nearest cent.)

A) $3.72 per direct labor hour

B) $1.40 per machine hour

C) $2.25 per machine hour

D) $0.22 per direct labor hour

+1
Answers (1)
  1. 24 November, 07:59
    0
    B) $1.40 per machine hour

    Explanation:

    Total machine hours = 29,000 + 48,000 = 77,000

    Predetermined overhead allocation rate = Total estimated overhead costs / Total estimated quantity of the overhead allocation base

    = $108,000 / 77,000 machine hours

    = $1.40 per machine hour
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The company allocates manufacturing overhead using a single plantwide rate with machine hours as the allocation base. Estimated overhead ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers