Ask Question
25 June, 14:40

The chattanooga furniture store gets an average of 72 72 customers per shift. marilyn helms, the manager, wants to calculate whether she should hire 1 1 , 2 2 , 3 3 , or 4 4 salespeople. she has determined that average waiting times will be 10 10 minutes with one salesperson, 6 6 minutes with two salespeople, 3 3 minutes with three salespeople, and 2 2 minutes with four salespeople. she has estimated the cost per minute that customers wait at $ 1 1. the cost per salesperson per shift (including fringe benefits) is $ 80 80.

+1
Answers (1)
  1. 25 June, 15:50
    0
    3 Sales people

    Explanation:

    The calculation of total cost per shift is shown below:-

    1st sales 2nd sales 3rd sales 4th sales

    person person person person

    Average Waiting

    Time 10 minutes 6 minutes 3 minutes 2 minutes

    Total waiting

    Cost $720 $432 $216 $144

    (72 * $1 * 10) (72 * $1 * 6) (72 * $1 * 3) (72 * $1 * 2)

    Add: Total labor

    Cost 80 $160 $240 $320

    ($80 * 1) ($80 * 2) ($80 * 3) ($80 * 4)

    Total cost $800 $592 $456 $464

    Thus, 3 servers have the lowest cost, so that the overall cost per change with 3 Sales people is chosen.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The chattanooga furniture store gets an average of 72 72 customers per shift. marilyn helms, the manager, wants to calculate whether she ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers