Effective use of MRP and other dependent demand models does NOT require which of the following? lead times inventory availability master production schedule cost of individual components bill of materials

+4
Answers (1)
  1. 12 February, 17:05
    0
    The correct answer is letter "D": cost of individual components.

    Explanation:

    Material Requirement Planning (MRP) is a solution for a common production problem: controlling and coordinating the flow of the necessary materials so they will be available whenever necessary without having a surplus in inventory.

    For this technique to be implemented it is necessary each product structure calculating the components, materials, and quantities needed for all of them. All that information is comprised in a document called Bill of Materials (BOM).

    The BOM does not include the individual costs of components.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Effective use of MRP and other dependent demand models does NOT require which of the following? lead times inventory availability master ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.