A proposed nuclear power plant will cost $2.9 billion to build and then will produce cash flows of $370 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $970 million. What is project NPV if the discount rate is 4%? What if it is 16%? (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Enter your answers in billions rounded to 3 decimal places.)

+1
Answers (1)
  1. 22 May, 10:01
    0
    This question can be solved using a financial calculator. Use the cashflow button (CF) on Texas Instruments BA II Plus with the following inputs;

    CF0 = - 2,900,000

    C01 = 370,000,000

    F0,1 = 14 (Since the recurring equal cashflows occurs for 14 years; use frequency function and input 14)

    For year 15, find the net cashflows since there's a cost of $970 million;

    C02 = $370 - $970 = - $600 million

    I = 4%

    then compute net present value; CPT NPV = $3,572,296,782 or $3.572 Billion

    If 16%, everything remains the same except for I = 16%

    NPV = $1,955,329,577 or $1.955 Billion
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A proposed nuclear power plant will cost $2.9 billion to build and then will produce cash flows of $370 million a year for 15 years. After ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.