Compute the takt time for a system where the total time per shift is 410 minutes, there is one shift, and workers are given 3 14-minute breaks and 40 minutes for lunch. daily demand is 357 units.

+3
Answers (1)
  1. 19 March, 17:14
    0
    55 seconds, or 55.13 seconds. The available production time per day is 328 minutes - total time, 410 minutes, minus the time allotted for breaks, 82 minutes. Converted into seconds (by multiplying with 60), there are 19680 seconds available for production. The takt time is found by dividing this number with the daily demand, 357 units.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Compute the takt time for a system where the total time per shift is 410 minutes, there is one shift, and workers are given 3 14-minute ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.