Scorpion production company planned to use 1 yard of plastic per unit budgeted at $81 a yard. however, the plastic actually cost $80 per yard. the company actually made 3,900 units, although it had planned to make only 3,300 units. total yards used for production were 3,960. how much is the total materials variance?

+1
Answers (1)
  1. 2 December, 17:27
    0
    The total material variance is calculated through the equation,

    total material variance = (SP x SQ) - (AP x AQ)

    where SP and SQ are standard price and standard quantity, respectively and AP and AQ are actual price and actual quantity, respectively.

    Substituting the known values,

    total material variance = ($81 x 3300) - ($80 x 3900)

    = - $44,700
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Scorpion production company planned to use 1 yard of plastic per unit budgeted at $81 a yard. however, the plastic actually cost $80 per ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.