A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct? There are four paths in this network. (T/F)

+1
Answers (1)
  1. 22 January, 17:15
    0
    True

    Explanation:

    There are four paths in this network. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.