Ask Question
19 May, 21:37

Which of the following strategies should the Government NOT consider during IP implementation?

a. Consider data rights as a? priced option? to the contract.

b. Negotiate data rights after a contractor has been notified of selection.

c. Outline the Government's data rights needs in the RFP.

d. Make technical data rights a source selection criterion

+5
Answers (1)
  1. 19 May, 23:03
    0
    Correct answer is (b). Negotiate data rights after a contractor has been notified of selection.

    Explanation:

    During IP implementation, it is expedient for government to outline and negotiate the data before selection and notification of contractor to ensure effective planning.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following strategies should the Government NOT consider during IP implementation? a. Consider data rights as a? priced option? ...” in 📙 History if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers