Lauren coordinates a construction projects for a cement company. A government project requires constructing two rectangular concrete slabs of dimensions 24 * 24 * 1 feet. Additionally, the company sends a 20% surplus of concrete to ensure the job can be completed. If a cement truck can carry a maximum of 8 cubic yards of cement, what's the fewest number of trucks that Lauren should send? A) 1 B) 2 C) 3 D) 4 E) 5

+2
Answers (1)
  1. 18 December, 23:37
    0
    7

    Step-by-step explanation:

    Total concrete for slabs

    24 * 24 * 1 = 576 ft³

    Additional 20 %

    By rule of three

    if 576 ⇒ 100

    x? ⇒ 20 x = 115,2

    And there are 2 slabs, the total volume of concrete is:

    Q (t) = 2 * (576 + 115,2) Q (t) = 1382,4 ft³ (1)

    If the truck can carry a maximum of 8 yd³, as 1 ft³ = 0,037 yd³

    then a truck can carry a maximum of

    8 / 0,037 = 216,21 ft³

    Now the total quantity is 1382,4

    Then

    1382,4/216,21 = 6,39

    And as nobody can send a fraction of a truck, the fewest number of truck is 7
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Lauren coordinates a construction projects for a cement company. A government project requires constructing two rectangular concrete slabs ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.