Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations? The task times for the eight tasks that make up the job are 8, 4, 7, 9, 10, 14, 12, and 8 minutes, and the cycle time is 8 minutes.

+2
Answers (1)
  1. 12 November, 10:42
    0
    the theoretical minimum number of workstations is 9.

    Step-by-step explanation:

    to determine the theoretical minimum number of workstations we use the formula below:

    Number of workstations = sum of total task time / cycle time

    Given information:

    Task times = 8, 4, 7, 9, 10, 14, 12, and 8 minutes

    sum of total task time = 8+4+7+9+10+14+12+8

    = 72 minutes

    cycle time = 8 minutes

    Thus,

    Number of workstations = 72 minutes / 8 minutes

    = 9
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations? The task times for ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.