A contractor estimated that one of his two brick layers would take 9 hours to build a certain wall and the other 10 hours. However, he knew from experience that when they worked together, 10 fewer bricks were laid per hour. Since he was in a hurry, he put both men on the job and found it took exactly 5 hours to build the wall. How many bricks did the wall contain?

+2
Answers (1)
  1. 26 July, 01:09
    0
    900

    Step-by-step explanation:

    Assume x brick

    X * (1/9+1/10) 一 10=X/5

    X (19/90-1/5) = 10

    X * (1/90) = 10

    X=900
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A contractor estimated that one of his two brick layers would take 9 hours to build a certain wall and the other 10 hours. However, he knew ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.