A manager wants to determine the number of containers to use for incoming parts for a kanban system to be installed next month. The process will have a usage rate of 83 pieces per hour. Because the process is new, the manager has assigned an inefficiency factor of. 18. Each container holds 53 pieces and it takes an average of 80 minutes to complete a cycle. How many containers should be used? (Round up your answer to the next whole number.) Number of containers As the system improves, will more or fewer containers be required? More Fewer

+4
Answers (1)
  1. 19 March, 15:27
    0
    2 containers should be used

    As the system improves, neither more or fewer containers be required

    Step-by-step explanation:

    According to the given data we have the following:

    D=83 pieces per hour.

    T=80 minutes=1.33 hour

    X=0.18

    C=53

    In order to calculate how many containers should be used we would have to use the following formula:

    Number of containers=DT (1+X)

    C

    Number of containers = (83) (1.33) (1+0.18)

    53

    Number of containers=2.45=2

    2 containers should be used.

    As the system improves, neither more or fewer containers be required
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A manager wants to determine the number of containers to use for incoming parts for a kanban system to be installed next month. The process ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers