Two groups of workers are painting a bridge in the bay. The first group is responsible for painting the north side of the bridge, and the second group is responsible for painting the south side of the bridge. The first group has already painted 2 kilometers of the bridge and is painting 2 additional kilometers per day. The second group has already painted 5 kilometers of the bridge and is painting 1 additional kilometer per day. When the two groups have painted the same amount of the bridge, how much of the bridge will they each have painted?

+5
Answers (1)
  1. 18 May, 04:47
    0
    They will each have painted 8 km. This goal will be met on Day 4.

    Step-by-step explanation:

    Group A | Group B

    Start: 2 | Start: 5 Day 1

    2 + 2 = 4 | 5 + 1 = 6 Day 2

    4 + 2 = 6 | 6 + 1 = 7 Day 3

    6 + 2 = 8 | 7 + 1 = 8 Day 4
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Two groups of workers are painting a bridge in the bay. The first group is responsible for painting the north side of the bridge, and the ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers