A construction worker estimates that a kitchen remodel will take 1 person 112 hours. If 4 people work on the job for 7 hours a day, how many days will it take for them to complete the job?

+1
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A construction worker estimates that a kitchen remodel will take 1 person 112 hours. If 4 people work on the job for 7 hours a day, how ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.