Solve the word problem.

Lee can frame a cabin in 4 days less than Ron. When they work together, they will do the job in 4 days. How long would each of them take to frame the cabin alone?

Ron

a0 days

Lee

a1 days

+4
Answers (1)
  1. 9 August, 22:05
    0
    Ron: 6+2√5 days ≈ 10.47 days

    Lee: 2+2√5 days ≈ 6.47 days

    Step-by-step explanation:

    Let L represent the number of days it takes Lee to frame a cabin. Then it take L+4 days for Ron to frame it. Working together, they take 4 days. Then their rates, in cabins per day, add up as ...

    1/L + 1 / (L+4) = 1/4

    Multiplying by the product of denominators, we get ...

    4 (L+4) + 4L = L (L+4)

    Subtracting the left side gives ...

    L^2 - 4L - 16 = 0

    Completing the square, we can write this as ...

    L^2 - 4L + 4 = 20

    (L - 2) ^2 = 20

    L = 2 + √20 = 2 + 2√5 ≈ 6.47

    Lee takes 2+2√5 ≈ 6.47 days to frame a cabin.

    Ron takes 6+2√5 ≈ 10.47 days to frame a cabin.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Solve the word problem. Lee can frame a cabin in 4 days less than Ron. When they work together, they will do the job in 4 days. How long ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.