T takes about 14 person-hours of labor to break up a driveway and clear away the rubble. It takes about 8 person-hours of labor to pour and smooth concrete for the new driveway. About how many person-hours of labor does it take to break up a driveway, clear away the rubble, pour the concrete, and smooth the concrete? 6

+2
Answers (1)
  1. 31 August, 13:50
    0
    For this case what you must do is add the number of hours to perform the different activities.

    We have then:

    14 person-hours of labor to break up to driveway and clear away the rubble.

    8 person-hours of labor to pour and smooth concrete for the new driveway.

    Adding both activities we have

    14 + 8 = 22

    answer

    it takes to break up to driveway, clear away the rubble, pour the concrete, and smooth the concrete about 22 person-hours of labor
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “T takes about 14 person-hours of labor to break up a driveway and clear away the rubble. It takes about 8 person-hours of labor to pour and ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.