A toy manufacturer wants to minimize her cost for producing two lines of toy airplanes. Because of the supply of materials, no more than 40 Flying Bats can be built each day, and no more than 60 Flying Falcons can be built each day. There are enough workers to build at least 70 toy airplanes each day. It costs $12 to manufacture a Flying Bat and $8 to build a Flying Falcon. What is the minimum possible cost each day?

+5
Answers (1)
  1. 17 November, 19:39
    0
    Since Flying Falcon cost ($8) is cheaper than Flying Bat ($12), then the minimum possible cost each day would be the maximum possible Flying Falcon produced.

    The maximum flying falcon produces is 60/day. Then, the amount of flying bat produced would be:

    total = falcon + bat

    70 = 60+bat

    bat = 70-60 = 10

    The minimum possible cost: falcon * falcon_cost + bat * bat_cost = 60*$8 + 10*$12 = $480+$120 = $600
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A toy manufacturer wants to minimize her cost for producing two lines of toy airplanes. Because of the supply of materials, no more than 40 ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers