Ask Question
15 February, 05:15

Electrical work on a project cannot start until all of the electrical supplies have arrived on site. The relationship between the acquisition of all supplies and the electrical work is:a) Finish-Start b) Start-Finish c) Finish-Finish d) Start-Start

+5
Answers (1)
  1. 15 February, 07:02
    0
    A

    Explanation:

    Finish-Start

    Finish to Start is a Logical Relationship in which a Successor Activity cannot start until a Predecessor Activity has finished. What it really means in simple terms we can say that, the Start of a Successor Activity is Dependent on Finish of the Predecessor Activity.

    The acquisition of all supplies which is the predecessor activity must finish before the electicalmwork can start which is the successor activity.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Electrical work on a project cannot start until all of the electrical supplies have arrived on site. The relationship between the ...” in 📙 Physics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers