Electric power is to be generated by installing a hydraulic turbine generator at a site 120 m below the free surface of a large water reservoir that can supply water at a rate of 2400 kg/s steadily. Determine the power generation potential.

+1
Answers (1)
  1. 3 March, 22:49
    0
    2.82 * 10^6 watt

    Explanation:

    H = 120 m,

    Mass per second = 2400 kg/s

    Power = work / time

    Power = m g H / t

    Power = 2400 * 9.8 * 120 / 1

    Power = 2.82 * 10^6 Watt
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Electric power is to be generated by installing a hydraulic turbine generator at a site 120 m below the free surface of a large water ...” in 📙 Physics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.