The EHR that is currently being selected was initially planned for the inpatients at the hospital. Now the CIO has instructed the project management team to purchase one that works for both the inpatient and ambulatory services. This is an example of

+1
Answers (1)
  1. 26 August, 05:46
    0
    This is an example of scope creep.

    Explanation:

    In project management, scope creep signifies the changes, uncontrolled or continuous growth in the scope of a project, at any time after the initiation of the project. This can take place when the project's scope is not adequately documented, defined, or monitored.

    The main reasons for scope creep are poor requirements analysis, underestimating the complexity of the project, not involving users early enough, and lack of change control. Thus, the given case is an illustration of scope creep.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The EHR that is currently being selected was initially planned for the inpatients at the hospital. Now the CIO has instructed the project ...” in 📙 Biology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers