West company estimates that overhead costs for the next year will be $5,240,000 for indirect labor and $550,000 for factory utilities. the company uses machine hours as its overhead allocation base. if 150,000 machine hours are planned for this next year, what is the company's plantwide overhead rate? $.0259 per machine hour. $34.93 per machine hour. $38.60 per machine hour. $.2727 per machine hour. $3.67 per machine hour.

+3
Answers (2)
  1. 10 November, 16:05
    0
    Predetermined oH rate is

    (5,240,000+550,000) : 150,000

    =38.6 per machine hour
  2. 10 November, 16:38
    0
    We need overhead rate in total cost/machine hour, so

    total cost = 5,240,000+550,000 = 5,790,000

    total machine hours = 150,000

    Average overhead = 5,790,000 / 150,000

    =$38.60 / machine hour.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “West company estimates that overhead costs for the next year will be $5,240,000 for indirect labor and $550,000 for factory utilities. the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers