Shane industries prepared a fixed budget of 60,000 direct labor hours, with estimated overhead costs of $300,000 for variable overhead and $90,000 for fixed overhead. shane then prepared a flexible budget at 57,000 labor hours. how much is total overhead costs at this level of activity?

+5
Answers (1)
  1. 12 September, 01:33
    0
    Total overhead

    ((300,000:60,000) * 57,000) + 90,000

    =375,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Shane industries prepared a fixed budget of 60,000 direct labor hours, with estimated overhead costs of $300,000 for variable overhead and ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.