You are targeting a total production volume increase of 10% in the next 7 days compared to the last 7 days' actual production volume. assuming you maintain the same productivity rate as last week for the next 7 days, approximately how many scheduled hours will you need to schedule to achieve this goal?

+1
Answers (1)
  1. 29 January, 04:30
    0
    Let x = current producton rate in vol/hour.

    Then the current production volume in 7 days is

    V = (24*7) x = 168x

    The targeted production increase is 10%, so the new weekly volume is

    1.1 * (168x) = 184.8x

    Let y = the extra hours required to meet the new targeted volume. Therefore

    (168 + y) x = 184.8x

    Divide by x.

    168 + y = 184.8

    y = 184.8 - 168 = 16.8 hours

    Answer:

    For the week:

    The scheduled hours is 184.8

    The extra hours is 16.8
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “You are targeting a total production volume increase of 10% in the next 7 days compared to the last 7 days' actual production volume. ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.