The predetermined overhead rate for concord corporation is $5, comprised of a variable overhead rate of $3 and a fixed rate of $2. the amount of budgeted overhead costs at normal capacity of $150000 was divided by normal capacity of 30000 direct labor hours, to arrive at the predetermined overhead rate of $5. actual overhead for june was $8288 variable and $5040 fixed, and 1400 units were produced. the direct labor standard is 2 hours per unit produced. the total overhead variance is

+5
Answers (1)
  1. 20 February, 12:14
    0
    Actual overhead=8,288+5,040=13,328

    Estimated overhead

    5 * (2*1,400)

    5*2800 direct labor hours

    =14,000

    The total overhead variance

    14,000-13,328

    =672 over applied
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The predetermined overhead rate for concord corporation is $5, comprised of a variable overhead rate of $3 and a fixed rate of $2. the ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers