13 July, 09:50

Strong company applies overhead based on machine hours. at the beginning of 20x1, the company estimated that manufacturing overhead would be $500,000, and machine hours would total 20,000. by 20x1 year-end, actual overhead totaled $525,000, and actual machine hours were 25,000. on the basis of this information, the 20x1 predetermined overhead rate was:

+3
Answers (1)
  1. 13 July, 10:44
    0
    Hi there

    predetermined overhead rate =

    estimated manufacturing overhead:

    estimated machine hours

    So

    predetermined overhead rate =

    500,000:20,000=25 per machine hour

    Good luck!
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Strong company applies overhead based on machine hours. at the beginning of 20x1, the company estimated that manufacturing overhead would ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.