Ask Question
26 March, 01:18

Import auto company held a 4-day training program for 20 employees. all employees were paid their regular wages for the time they were released from their regular work. these wages totaled $5,897.64 for the group. refreshments and lunch were served at a cost of $45.50 per person each day. the instructor who conducted the training charged $500.00 per day. supplies and equipment for the program totaled $8.00 per person. travel expenses for the group totaled $22,457.63. what was the total cost for the seminar to the nearest cent?

+3
Answers (1)
  1. 26 March, 04:34
    0
    Total wages $ 5,897.64

    refreshments and lunch = $ 45.50 * 4 * 20 = $3640

    Instructor = $500 * 4 = $2000

    Supplies and equipment = $ 8 * 20 = $ 160

    Travel expenses = $22,457.63

    therefore, the total cost of the training will be

    $5897.64 + $3640 + $2000+$160 + $22,457.63 = $34,155.27
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Import auto company held a 4-day training program for 20 employees. all employees were paid their regular wages for the time they were ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers