What does "residual risk" mean in the rm process?

+3
Answers (1)
  1. 13 October, 23:33
    0
    RM process stands for risk management process. The RM process includes identifying and controlling risks arising as a result of the operation.

    As "residual risk" are denoted the remains of a risk and danger on which a response has been performed.

    residual risk=inherent risk - impact of risk controls