An order for 50 units of product a and 60 of b has been placed. there are currently 25 units of product b on hand. each a requires 2 units of part c; each b requires 5 units of

c. there are 160 units of c available. what are the net requirements for c?

+4
Answers (1)
  1. 27 January, 06:39
    0
    To determine the net requirement for c, we determine first the number of c’s that are required for the production of a and b given that there are already 25 units of b available.

    Number of c needed = (50 units of a) (2 c/unit of a) + (60 - 25 units of b) (5 c/unit of b)

    Number of c needed = 275 c’s

    There are currently 160 units of c; hence,

    Net requirement for c = 275 c - 160 c

    Net requirement for c = 115

    Answer: 115
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “An order for 50 units of product a and 60 of b has been placed. there are currently 25 units of product b on hand. each a requires 2 units ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.