Ask Question
9 December, 08:01

A project manager is managing a project that has reached the end of planning phase. The work scope has been agreed to and definitive cost estimates have been completed for the project. The total estimated cost of the project is $100,000. It is reasonable to expect that the project will not cost over which of the following value?

a. $100,000

b. $110,000

c. $125,000

d. $175,000

+1
Answers (1)
  1. 9 December, 10:35
    0
    125

    Explanation:

    It waz the totale over estimate
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A project manager is managing a project that has reached the end of planning phase. The work scope has been agreed to and definitive cost ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.