Potthast Company uses a two-stage system to allocate its overhead to products. The company uses machine hours in the fabrication department and direct labor hours in the assembly department to allocate overhead costs to Work-in-Process. During the current year, the company incurred $50,000 of overhead costs in the fabrication department and $75,000 of overhead costs in the assembly department. The company also reported the following results in the production of its standard and deluxe bicycles. Standard DeluxeMachine hours (fabrication) 1,000 4,000Direct labor hours (assembly) 4,000 6,000Using a two-stage cost allocation, how much overhead should be allocated to the production of deluxe bicycles in the current year? A) $50,000B) $40,000C) None of these. D) $85,000E) $75,000

+3
Answers (1)
  1. 2 December, 20:43
    0
    D) $85,000

    Explanation:

    Standard Deluxe

    Machine hours (fabrication) 1,000 4,000

    Direct labor hours (assembly) 4,000 6,000

    If the company spent $50,000 in overhead costs in the fabrication department, then 20% must be allocated to standard bicycles ($10,000) and 80% to deluxe bicycles ($40,000).

    If the company spent $75,000 in overhead costs in the assembly department, then 40% must be allocated to standard bicycles ($30,000) and 60% to deluxe bicycles ($45,000).

    The total overhead allocated to standard bicycles = $10,000 + $30,000 = $40,000

    The total overhead allocated to deluxe bicycles = $40,000 + $45,000 = $85,000
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Potthast Company uses a two-stage system to allocate its overhead to products. The company uses machine hours in the fabrication department ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.