The production budget for Manner Company shows units to be produced as follows: July, 650; August, 710; and September, 570. Each unit produced requires one hour of direct labor. The direct labor rate is currently $16 per hour but is predicted to be $16.75 per hour in September. Prepare a direct labor budget for the months July, August, and September.

+3
Answers (1)
  1. 31 May, 21:26
    0
    Results are below.

    Explanation:

    Giving the following information:

    Production:

    July = 650 units

    August = 710 units

    September = 570 units

    Each unit produced requires one hour of direct labor.

    he direct labor rate is currently $16 per hour but is predicted to be $16.75 per hour in September.

    We need to prepare the direct labor budget:

    July:

    Direct labor = (650*1) * 16 = $10,400

    August:

    Direct labor = (710*1) * 16 = $11,360

    September:

    Direct labor = (570*1) * 16.75 = $9,547.5
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The production budget for Manner Company shows units to be produced as follows: July, 650; August, 710; and September, 570. Each unit ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.