Waterway Industriesbudgeted manufacturing costs for 70000 tons of steel are: Fixed manufacturing costs $50000 per month Variable manufacturing costs $12 per ton of steel Waterwayproduced 55000 tons of steel during March. How much is the flexible budget for total manufacturing costs for March?
A. $890000
B. $695000
C. $660000
D. $710000