Ask Question
24 January, 14:26

Which of the following statements regarding time-cost tradeoffs in CPM networks is false? A. Crashing shortens project duration by assigning more resources to critical tasks. B. Crashing sometimes has the reverse result of lengthening the project duration. C. A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time. D. Crashing must consider the impact of crashing an activity on all paths in the network. E. Activities not on the critical path can become critical after crashing takes place.

+1
Answers (1)
  1. 24 January, 16:03
    0
    B. Crashing sometimes has the reverse result of lengthening the project duration
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which of the following statements regarding time-cost tradeoffs in CPM networks is false? A. Crashing shortens project duration by ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers