A contractor figured materials for a job would cost $2,415. He also estimated labor for the same job would cost $1,832. If he adds 18% to cover overhead and profit, how much will he charge the customer for this job?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A contractor figured materials for a job would cost $2,415. He also estimated labor for the same job would cost $1,832. If he adds 18% to ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.