Ask Question
23 February, 06:17

A hydraulic shovel will beused to excavate sandy clay and load it into 12-BCY dump trucks. The shovel's production at 100%efficiency is estimated to be 300 BCY/h, and job efficiency is 0.80. Truck traveltime is estimated to be 8.0 min, and truck fixed-cycle time (excluding loading) is estimated to be 2.0 min. Equipment costs for the shovel and trucks are $40/h and $20/h, respectively. A. How many trucks are theoretically required to obtain maximum production? B. What is the expected production of the system in bank measure using this number of trucks? C. What is the expected unit loading and hauling cost ($/BCY) ?

+3
Answers (1)
  1. 23 February, 07:01
    0
    a)

    Find the truck load time using relation

    load time = Truck capacity/Shovel production

    Substitute 12 BCY for truck capacity and 300 BCY/h for shovel production

    load time = (12 BCY) / (300 BCY/h) = 0.04h=0.04 x 60min=2.4min

    Find the truck cycle time using relation

    Truck cycle time = Load time + Travel + Fixed cycle time

    Substitute 2.4 min for load time 8 min for travel time and 2 min for fixed cycle time

    Truck cycle time = 2.4 + 8min + 2 min = 12.4 min

    Find the number of trucks required using relation

    Number of trucks = Truck cycle time/Load time

    Substitute 12.4 min for truck cycle time and 2.4 min for load time

    Number of trucks = 12.4/2.4=5.2=6

    Therefore, the theoritical number of trucks required is 6

    b)

    Find the expected production using the relation

    Production = shovel production (BCM/h) x Job efficiency

    Substitute 300 BCY/h for shovel production and 0.80 for job efficiency

    Production = 300 BCY/h x 0.80 = 240 BCY/h

    Therefore, the expected production is 240 BCY/h

    c)

    Find the total cost of equipment per hour using relation

    Total cost per hour = cost of shovel per hour + cost of 6 trucks per hour

    Substitute $40 for cost of shovel per hour and $20 for cost of one truck per hour

    Total cost = $40 + (6 x $20) = $160

    calculate the unit cost of loading and hauling using relation

    Unit cost loading and hauling = Equipment cost per hour/Equipment production per hour

    Substitute $160 for the total equipment cost per hour 183.2 BCM/h for equipment production per hour

    unit cost loading and hauling = $160 / (240 BCY/h) = $0.667 BCY

    Therefore, the uniy cost of loading and hauling is $0.667 BCY
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A hydraulic shovel will beused to excavate sandy clay and load it into 12-BCY dump trucks. The shovel's production at 100%efficiency is ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers