During which stage of team development do members accept that they are part of a project group but resist the constraints that the project and the group put on their individuality?

+5
Answers (1)
  1. 27 March, 16:26
    0
    Answer: Storming.

    Explanation:

    The stages of team development are; forming, storming, norming and performing stages. The storming stage is the stage just after the team has been formed when individuals in the team tend to clash with each other based on differences in individual characters or interests. After the storming stage has passed things tends to normalize in the team.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “During which stage of team development do members accept that they are part of a project group but resist the constraints that the project ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.