Ask Question
30 June, 19:05

Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time - 21 days Which of the following statements is TRUE about activity G? a. Activity G takes 14 days to complete. b. Activity G has a slack time of 8 days. c. Activity G is on the critical path. d. Activity G takes 2 days to complete.

+4
Answers (1)
  1. 30 June, 20:16
    0
    The correct answer is Activity G has s slack time of 8 days.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time ...” in 📙 Business if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers